Present Worth with Salvage Value
I would like to know how to consider the "Salvage Value" in the following question while calculating the present and future values.
here is the question:
We are planning to build a new bridge. Construction is to start in 2015 and is expected to take 4 years at a cost of $25 million per year.
After construction is completed, the cost of operation and maintenance is expected to be $2.5 million for the first year, and increase by 2.8% per year thereafter.
The salvage value of the bridge at the end of year 2048 is estimated to be $5 million.
Consider the present to be the end of 2013/beginning of 2014 and the interest rate to be 8%.
a- Draw a cash flow diagram for this project (from present till end of year 2048)
b- find the Present Worth
c- find the Future Worth
HERE IS WHAT I DID:
we need to find P2013 (Present Worth at this time)
P2013 = P2015 (1+i)^n = P2015 (1+0.08)^2
P2015 = A1 (P1|A1 8%,33) + A2 (P2|A2 2.8%,8%,29)
P2015 = $ 324,433,747.65
P2013 = P2015 (1+0.08)^2 = $ 378,419,523.26
Now the question is where to consider the $5 million salvage value in this formula? Is my calculation correct?
economics
add a comment |
I would like to know how to consider the "Salvage Value" in the following question while calculating the present and future values.
here is the question:
We are planning to build a new bridge. Construction is to start in 2015 and is expected to take 4 years at a cost of $25 million per year.
After construction is completed, the cost of operation and maintenance is expected to be $2.5 million for the first year, and increase by 2.8% per year thereafter.
The salvage value of the bridge at the end of year 2048 is estimated to be $5 million.
Consider the present to be the end of 2013/beginning of 2014 and the interest rate to be 8%.
a- Draw a cash flow diagram for this project (from present till end of year 2048)
b- find the Present Worth
c- find the Future Worth
HERE IS WHAT I DID:
we need to find P2013 (Present Worth at this time)
P2013 = P2015 (1+i)^n = P2015 (1+0.08)^2
P2015 = A1 (P1|A1 8%,33) + A2 (P2|A2 2.8%,8%,29)
P2015 = $ 324,433,747.65
P2013 = P2015 (1+0.08)^2 = $ 378,419,523.26
Now the question is where to consider the $5 million salvage value in this formula? Is my calculation correct?
economics
add a comment |
I would like to know how to consider the "Salvage Value" in the following question while calculating the present and future values.
here is the question:
We are planning to build a new bridge. Construction is to start in 2015 and is expected to take 4 years at a cost of $25 million per year.
After construction is completed, the cost of operation and maintenance is expected to be $2.5 million for the first year, and increase by 2.8% per year thereafter.
The salvage value of the bridge at the end of year 2048 is estimated to be $5 million.
Consider the present to be the end of 2013/beginning of 2014 and the interest rate to be 8%.
a- Draw a cash flow diagram for this project (from present till end of year 2048)
b- find the Present Worth
c- find the Future Worth
HERE IS WHAT I DID:
we need to find P2013 (Present Worth at this time)
P2013 = P2015 (1+i)^n = P2015 (1+0.08)^2
P2015 = A1 (P1|A1 8%,33) + A2 (P2|A2 2.8%,8%,29)
P2015 = $ 324,433,747.65
P2013 = P2015 (1+0.08)^2 = $ 378,419,523.26
Now the question is where to consider the $5 million salvage value in this formula? Is my calculation correct?
economics
I would like to know how to consider the "Salvage Value" in the following question while calculating the present and future values.
here is the question:
We are planning to build a new bridge. Construction is to start in 2015 and is expected to take 4 years at a cost of $25 million per year.
After construction is completed, the cost of operation and maintenance is expected to be $2.5 million for the first year, and increase by 2.8% per year thereafter.
The salvage value of the bridge at the end of year 2048 is estimated to be $5 million.
Consider the present to be the end of 2013/beginning of 2014 and the interest rate to be 8%.
a- Draw a cash flow diagram for this project (from present till end of year 2048)
b- find the Present Worth
c- find the Future Worth
HERE IS WHAT I DID:
we need to find P2013 (Present Worth at this time)
P2013 = P2015 (1+i)^n = P2015 (1+0.08)^2
P2015 = A1 (P1|A1 8%,33) + A2 (P2|A2 2.8%,8%,29)
P2015 = $ 324,433,747.65
P2013 = P2015 (1+0.08)^2 = $ 378,419,523.26
Now the question is where to consider the $5 million salvage value in this formula? Is my calculation correct?
economics
economics
asked Nov 18 '14 at 18:35
Vahid GarshasbiVahid Garshasbi
31
31
add a comment |
add a comment |
1 Answer
1
active
oldest
votes
I would calculated the future value at the end of the year 2048 ($C_{2048}$) an and after that I would calculate the present value.
Construction costs:
The construction period goes from 2015 to 2018. $C_{2018}^C=25,000,000cdot frac{1-1.08^4}{1-1.08}$
$C_{2048}^C=25,000,000cdot frac{1-1.08^4}{1-1.08}cdot 1.08^{48-18}=25,000,000cdot frac{1-1.08^4}{1-1.08}cdot 1.08^{30}$
Costs of operation and maintanace
It has to be made 30(=48-19+1) payments. And the formula with increasing payments is
$C_n=r cdot frac{g^n-q^n}{g-q}$
$C_{2048}^{OM}=2,500,000cdot frac{1.028^{30}-1.08^{30}}{1.028-1.08}$
salvage value
The salvage value at 2048 is just $P_{2048}^S=5,000,000$
The value of all cash flows in 2048 is $C_{2048}^T=-C_{2048}^C-C_{2048}^{OM}+C_{2048}^S$
The value of all cash flows at the beginning of 2014 is $P_{2014}^T=frac{C_{2048}^T}{1.08^{48-14}}$
thank you so much.So the Future Worth will be negative, is the Present Worth negative as well?
– Vahid Garshasbi
Nov 20 '14 at 1:49
@VahidGarshasbi Sure. This is always the case. The general equation is $PW=frac{FW}{(1+i)^t}$. $1+i$ is always positive. If the Future Worth is negative, then the Present Worth is negative as well. If If the Future Worth is positive, then the Present Worth is positive as well. That is one the reason, why you can judge a project by using the net present value method.
– callculus
Nov 20 '14 at 9:29
@VahidGarshasbi You are welcome.
– callculus
Nov 20 '14 at 20:42
add a comment |
Your Answer
StackExchange.ifUsing("editor", function () {
return StackExchange.using("mathjaxEditing", function () {
StackExchange.MarkdownEditor.creationCallbacks.add(function (editor, postfix) {
StackExchange.mathjaxEditing.prepareWmdForMathJax(editor, postfix, [["$", "$"], ["\\(","\\)"]]);
});
});
}, "mathjax-editing");
StackExchange.ready(function() {
var channelOptions = {
tags: "".split(" "),
id: "69"
};
initTagRenderer("".split(" "), "".split(" "), channelOptions);
StackExchange.using("externalEditor", function() {
// Have to fire editor after snippets, if snippets enabled
if (StackExchange.settings.snippets.snippetsEnabled) {
StackExchange.using("snippets", function() {
createEditor();
});
}
else {
createEditor();
}
});
function createEditor() {
StackExchange.prepareEditor({
heartbeatType: 'answer',
autoActivateHeartbeat: false,
convertImagesToLinks: true,
noModals: true,
showLowRepImageUploadWarning: true,
reputationToPostImages: 10,
bindNavPrevention: true,
postfix: "",
imageUploader: {
brandingHtml: "Powered by u003ca class="icon-imgur-white" href="https://imgur.com/"u003eu003c/au003e",
contentPolicyHtml: "User contributions licensed under u003ca href="https://creativecommons.org/licenses/by-sa/3.0/"u003ecc by-sa 3.0 with attribution requiredu003c/au003e u003ca href="https://stackoverflow.com/legal/content-policy"u003e(content policy)u003c/au003e",
allowUrls: true
},
noCode: true, onDemand: true,
discardSelector: ".discard-answer"
,immediatelyShowMarkdownHelp:true
});
}
});
Sign up or log in
StackExchange.ready(function () {
StackExchange.helpers.onClickDraftSave('#login-link');
});
Sign up using Google
Sign up using Facebook
Sign up using Email and Password
Post as a guest
Required, but never shown
StackExchange.ready(
function () {
StackExchange.openid.initPostLogin('.new-post-login', 'https%3a%2f%2fmath.stackexchange.com%2fquestions%2f1027945%2fpresent-worth-with-salvage-value%23new-answer', 'question_page');
}
);
Post as a guest
Required, but never shown
1 Answer
1
active
oldest
votes
1 Answer
1
active
oldest
votes
active
oldest
votes
active
oldest
votes
I would calculated the future value at the end of the year 2048 ($C_{2048}$) an and after that I would calculate the present value.
Construction costs:
The construction period goes from 2015 to 2018. $C_{2018}^C=25,000,000cdot frac{1-1.08^4}{1-1.08}$
$C_{2048}^C=25,000,000cdot frac{1-1.08^4}{1-1.08}cdot 1.08^{48-18}=25,000,000cdot frac{1-1.08^4}{1-1.08}cdot 1.08^{30}$
Costs of operation and maintanace
It has to be made 30(=48-19+1) payments. And the formula with increasing payments is
$C_n=r cdot frac{g^n-q^n}{g-q}$
$C_{2048}^{OM}=2,500,000cdot frac{1.028^{30}-1.08^{30}}{1.028-1.08}$
salvage value
The salvage value at 2048 is just $P_{2048}^S=5,000,000$
The value of all cash flows in 2048 is $C_{2048}^T=-C_{2048}^C-C_{2048}^{OM}+C_{2048}^S$
The value of all cash flows at the beginning of 2014 is $P_{2014}^T=frac{C_{2048}^T}{1.08^{48-14}}$
thank you so much.So the Future Worth will be negative, is the Present Worth negative as well?
– Vahid Garshasbi
Nov 20 '14 at 1:49
@VahidGarshasbi Sure. This is always the case. The general equation is $PW=frac{FW}{(1+i)^t}$. $1+i$ is always positive. If the Future Worth is negative, then the Present Worth is negative as well. If If the Future Worth is positive, then the Present Worth is positive as well. That is one the reason, why you can judge a project by using the net present value method.
– callculus
Nov 20 '14 at 9:29
@VahidGarshasbi You are welcome.
– callculus
Nov 20 '14 at 20:42
add a comment |
I would calculated the future value at the end of the year 2048 ($C_{2048}$) an and after that I would calculate the present value.
Construction costs:
The construction period goes from 2015 to 2018. $C_{2018}^C=25,000,000cdot frac{1-1.08^4}{1-1.08}$
$C_{2048}^C=25,000,000cdot frac{1-1.08^4}{1-1.08}cdot 1.08^{48-18}=25,000,000cdot frac{1-1.08^4}{1-1.08}cdot 1.08^{30}$
Costs of operation and maintanace
It has to be made 30(=48-19+1) payments. And the formula with increasing payments is
$C_n=r cdot frac{g^n-q^n}{g-q}$
$C_{2048}^{OM}=2,500,000cdot frac{1.028^{30}-1.08^{30}}{1.028-1.08}$
salvage value
The salvage value at 2048 is just $P_{2048}^S=5,000,000$
The value of all cash flows in 2048 is $C_{2048}^T=-C_{2048}^C-C_{2048}^{OM}+C_{2048}^S$
The value of all cash flows at the beginning of 2014 is $P_{2014}^T=frac{C_{2048}^T}{1.08^{48-14}}$
thank you so much.So the Future Worth will be negative, is the Present Worth negative as well?
– Vahid Garshasbi
Nov 20 '14 at 1:49
@VahidGarshasbi Sure. This is always the case. The general equation is $PW=frac{FW}{(1+i)^t}$. $1+i$ is always positive. If the Future Worth is negative, then the Present Worth is negative as well. If If the Future Worth is positive, then the Present Worth is positive as well. That is one the reason, why you can judge a project by using the net present value method.
– callculus
Nov 20 '14 at 9:29
@VahidGarshasbi You are welcome.
– callculus
Nov 20 '14 at 20:42
add a comment |
I would calculated the future value at the end of the year 2048 ($C_{2048}$) an and after that I would calculate the present value.
Construction costs:
The construction period goes from 2015 to 2018. $C_{2018}^C=25,000,000cdot frac{1-1.08^4}{1-1.08}$
$C_{2048}^C=25,000,000cdot frac{1-1.08^4}{1-1.08}cdot 1.08^{48-18}=25,000,000cdot frac{1-1.08^4}{1-1.08}cdot 1.08^{30}$
Costs of operation and maintanace
It has to be made 30(=48-19+1) payments. And the formula with increasing payments is
$C_n=r cdot frac{g^n-q^n}{g-q}$
$C_{2048}^{OM}=2,500,000cdot frac{1.028^{30}-1.08^{30}}{1.028-1.08}$
salvage value
The salvage value at 2048 is just $P_{2048}^S=5,000,000$
The value of all cash flows in 2048 is $C_{2048}^T=-C_{2048}^C-C_{2048}^{OM}+C_{2048}^S$
The value of all cash flows at the beginning of 2014 is $P_{2014}^T=frac{C_{2048}^T}{1.08^{48-14}}$
I would calculated the future value at the end of the year 2048 ($C_{2048}$) an and after that I would calculate the present value.
Construction costs:
The construction period goes from 2015 to 2018. $C_{2018}^C=25,000,000cdot frac{1-1.08^4}{1-1.08}$
$C_{2048}^C=25,000,000cdot frac{1-1.08^4}{1-1.08}cdot 1.08^{48-18}=25,000,000cdot frac{1-1.08^4}{1-1.08}cdot 1.08^{30}$
Costs of operation and maintanace
It has to be made 30(=48-19+1) payments. And the formula with increasing payments is
$C_n=r cdot frac{g^n-q^n}{g-q}$
$C_{2048}^{OM}=2,500,000cdot frac{1.028^{30}-1.08^{30}}{1.028-1.08}$
salvage value
The salvage value at 2048 is just $P_{2048}^S=5,000,000$
The value of all cash flows in 2048 is $C_{2048}^T=-C_{2048}^C-C_{2048}^{OM}+C_{2048}^S$
The value of all cash flows at the beginning of 2014 is $P_{2014}^T=frac{C_{2048}^T}{1.08^{48-14}}$
answered Nov 19 '14 at 13:05
callculuscallculus
17.9k31427
17.9k31427
thank you so much.So the Future Worth will be negative, is the Present Worth negative as well?
– Vahid Garshasbi
Nov 20 '14 at 1:49
@VahidGarshasbi Sure. This is always the case. The general equation is $PW=frac{FW}{(1+i)^t}$. $1+i$ is always positive. If the Future Worth is negative, then the Present Worth is negative as well. If If the Future Worth is positive, then the Present Worth is positive as well. That is one the reason, why you can judge a project by using the net present value method.
– callculus
Nov 20 '14 at 9:29
@VahidGarshasbi You are welcome.
– callculus
Nov 20 '14 at 20:42
add a comment |
thank you so much.So the Future Worth will be negative, is the Present Worth negative as well?
– Vahid Garshasbi
Nov 20 '14 at 1:49
@VahidGarshasbi Sure. This is always the case. The general equation is $PW=frac{FW}{(1+i)^t}$. $1+i$ is always positive. If the Future Worth is negative, then the Present Worth is negative as well. If If the Future Worth is positive, then the Present Worth is positive as well. That is one the reason, why you can judge a project by using the net present value method.
– callculus
Nov 20 '14 at 9:29
@VahidGarshasbi You are welcome.
– callculus
Nov 20 '14 at 20:42
thank you so much.So the Future Worth will be negative, is the Present Worth negative as well?
– Vahid Garshasbi
Nov 20 '14 at 1:49
thank you so much.So the Future Worth will be negative, is the Present Worth negative as well?
– Vahid Garshasbi
Nov 20 '14 at 1:49
@VahidGarshasbi Sure. This is always the case. The general equation is $PW=frac{FW}{(1+i)^t}$. $1+i$ is always positive. If the Future Worth is negative, then the Present Worth is negative as well. If If the Future Worth is positive, then the Present Worth is positive as well. That is one the reason, why you can judge a project by using the net present value method.
– callculus
Nov 20 '14 at 9:29
@VahidGarshasbi Sure. This is always the case. The general equation is $PW=frac{FW}{(1+i)^t}$. $1+i$ is always positive. If the Future Worth is negative, then the Present Worth is negative as well. If If the Future Worth is positive, then the Present Worth is positive as well. That is one the reason, why you can judge a project by using the net present value method.
– callculus
Nov 20 '14 at 9:29
@VahidGarshasbi You are welcome.
– callculus
Nov 20 '14 at 20:42
@VahidGarshasbi You are welcome.
– callculus
Nov 20 '14 at 20:42
add a comment |
Thanks for contributing an answer to Mathematics Stack Exchange!
- Please be sure to answer the question. Provide details and share your research!
But avoid …
- Asking for help, clarification, or responding to other answers.
- Making statements based on opinion; back them up with references or personal experience.
Use MathJax to format equations. MathJax reference.
To learn more, see our tips on writing great answers.
Some of your past answers have not been well-received, and you're in danger of being blocked from answering.
Please pay close attention to the following guidance:
- Please be sure to answer the question. Provide details and share your research!
But avoid …
- Asking for help, clarification, or responding to other answers.
- Making statements based on opinion; back them up with references or personal experience.
To learn more, see our tips on writing great answers.
Sign up or log in
StackExchange.ready(function () {
StackExchange.helpers.onClickDraftSave('#login-link');
});
Sign up using Google
Sign up using Facebook
Sign up using Email and Password
Post as a guest
Required, but never shown
StackExchange.ready(
function () {
StackExchange.openid.initPostLogin('.new-post-login', 'https%3a%2f%2fmath.stackexchange.com%2fquestions%2f1027945%2fpresent-worth-with-salvage-value%23new-answer', 'question_page');
}
);
Post as a guest
Required, but never shown
Sign up or log in
StackExchange.ready(function () {
StackExchange.helpers.onClickDraftSave('#login-link');
});
Sign up using Google
Sign up using Facebook
Sign up using Email and Password
Post as a guest
Required, but never shown
Sign up or log in
StackExchange.ready(function () {
StackExchange.helpers.onClickDraftSave('#login-link');
});
Sign up using Google
Sign up using Facebook
Sign up using Email and Password
Post as a guest
Required, but never shown
Sign up or log in
StackExchange.ready(function () {
StackExchange.helpers.onClickDraftSave('#login-link');
});
Sign up using Google
Sign up using Facebook
Sign up using Email and Password
Sign up using Google
Sign up using Facebook
Sign up using Email and Password
Post as a guest
Required, but never shown
Required, but never shown
Required, but never shown
Required, but never shown
Required, but never shown
Required, but never shown
Required, but never shown
Required, but never shown
Required, but never shown